TOWN OF WESTMORELAND

 

 

SUBDIVISION REGULATIONS

 

TABLE OF CONTENTS

 

 

 

Subdivision Regulations

 

SECTION I                 Authority and Purpose                                      1

SECTION II                Definitions                                                                    1

SECTION III               General Requirements                                                   2

SECTION IV              Subdivision Review Procedures                                    2

SECTION V                Submission Requirements                                              6

SECTION VI              Developments Having Regional Impact              7

SECTION VII             Special Flood Hazard Areas                                         7

SECTION VIII            Performance Guarantee                                                7

SECTION IX              Revocation of Planning Board Approval                        8

SECTION X                Administration and Enforcement                                    8

SECTION XI              Validity                                                             8

SECTION XII             Amendments                                                                8

SECTION XIII            Effective Date                                                               8

 

                                     

 

Regional Impact Criteria                                                                                   9

 

Appendices:

Minor Subdivision Checklist                                          10

Major Subdivision Checklist                                         11

Application for Lot Line/Boundary Adjustment  13

Request for Preapplication Review                                14

Application for Subdivision Review                               15

 

 

 

 

 

 

 

 

 

 

 

Adopted by the Westmoreland Planning Board

After Public Hearing on November 14, 2000

 

SUBDIVISION REGULATIONS

 

SECTION I                Authority and Purpose

 

Pursuant to the authority vested in the Westmoreland Planning Board by the voters of the Town of Westmoreland in August of 1972 and in accordance with the provisions of RSA 674:35 of the New Hampshire Revised Statutes Annotated, and as amended, the Westmoreland Planning Board adopts the following regulations governing the subdivision of land in the Town of Westmoreland, New Hampshire.  These regulations are designed to accomplish the purposes set forth in RSA 674:36 and for the purpose of protecting the health, safety, convenience, and economic and general welfare of our citizens.

 

SECTION II               Definitions

 

A.     Abutter:  Any person whose property if located in New Hampshire and adjoins or is directly across the street or stream from the land under consideration by the local land use board.  For purposes of receiving testimony only, and not for purpose of notification, the term “abutter” shall include any person who is able to demonstrate that his land will be directly affected by the proposal under consideration.

B.      Applicant:  The owner of record of the land to be subdivided, or his/her designated agent.

C.     Approval:  Recognition by the Planning Board, certified by written endorsement on the plat, that the plat meets the requirements of these Regulations and in the judgment of the Board satisfies all criteria of good planning and design.

D.      Approval, Conditional: Recognition by the Planning Board, certified by written endorsement on the plat, that the plat is not finally approved nor ready for filing with the Registry of Deeds until such time as certain conditions set forth by the Board are met.

E.      Board:  The Planning Board of the Town of Westmoreland.

F.      Lot Line/Boundary Adjustment: Adjustments to the boundary between adjoining properties where no new lot(s) are created.

G.     Plat:  The map, drawing or chart on which the plan of subdivision is presented to the Planning Board for approval, and which, if approved, will be submitted to the Register of Deeds of Cheshire County for recording.

H.     Right-of-Way:  A strip of land for which legal right of passage has been granted by the landowner to provide access to a lot, which lacks adequate frontage.

I.        Street:  A Class V or better highway for vehicular traffic as defined in RSA 231 which is laid out and maintained by the Town.

J.        Street Frontage: That continuous portion of a lot, which abuts a public street.  A right-of-way does not constitute frontage.

K.     Subdivision: The division of a lot, tract, or parcel of land into two (2) or more lots, plats, sites, or other divisions of land for the purpose, whether immediate or future, of sale or building development.  It includes resubdivision and, when appropriate to the context, relates to the process of subdividing or to the land or territory subdivided.  The division of a parcel of land held in common and subsequently divided into parts among several owners shall be deemed a subdivision.

L.      Subdivision, Major: A subdivision of four (4) or more lots, or one which involves the creation of new streets.

 

 

November 14, 2000                                                                                                     SD

M.    Subdivision, Minor: A subdivision of land into not more than three (3) lots for building development purposes, with no potential for resubdivision on an existing street; or one which does not involve the creation of new streets.

N.     Subdivision, Technical: A subdivision of land into two lots or sites for the purpose of conveying one such lot or site directly to an abutting landowner.  The parcel to be conveyed does not constitute a separate building lot; however, said parcel may be used for building development in conjunction with contiguous land owned by the abutter.

 

SECTION III             General Requirements for the Subdivision of Land

 

A.       Character of Land for Subdivision: Land of such character that it cannot, in the judgment of the Board, be safely used for building development purposes because of exceptional danger to health or peril from fire, flood, poor drainage, excessive slope, or other hazardous conditions, shall not be platted for residential, commercial, or industrial subdivision, nor for such other uses as may increase danger to life or property, or aggravate the flood hazard.

B.        Premature Subdivision: The Board may provide against such scattered or premature subdivision of land as would involve danger or injury to health, safety, or prosperity by reason of the lack of water supply, sewage disposal, drainage, transportation, schools, fire protection, or other public services which necessitate the excessive expenditure of public funds for the supply of such services (RSA 674:36.II(a).

C.       Preservation of Existing Features: Wherever feasible, suitable steps shall be taken to preserve and protect significant existing features such as trees, scenic points, stone walls, rock outcroppings, water bodies, and historic landmarks.  Where possible, the boundary line(s) should follow stone walls.

D.       Septic Systems and Water Supply

1.      It is the responsibility of the subdivider or his agent to provide the necessary state approvals for the installation and operation of an individual sewage disposal system.  In subdividing parcels with existing dwellings, the subdivider must demonstrate to the satisfaction of the Board that the existing septic system is in good working order.

2.      All new wells shall have a radius of seventy-five (75) feet, said radius to be located entirely on its lot.

 

SECTION IV             Subdivision Review Procedures

 

A.  Preliminary Conceptual Consultation            (Optional)

1.      The applicant may request a meeting with the Board to discuss a proposal in conceptual form and in general terms.  Although this phase is strictly optional, the Board strongly suggests that the applicant avail him/herself of the opportunity to resolve any issues at this early stage that might become a problem later on.  Such preapplication consultation shall be informal and directed toward:

a)      Reviewing the basic concepts of the proposal.

b)      Reviewing the proposal with regard to the master plan and zoning ordinance.

c)      Explaining the state and local regulations that may apply to the proposal.

 

 

November 14, 2000                                                                                                     SD

d)      Determination of the proposal as a major, minor, or technical subdivision, and the submission items that would re required.

2.      Preliminary conceptual consultation shall not bind the Applicant or the Board.  Such discussion may occur without formal public notice, but must occur only at a posted meeting of the Board.

 

B.  Design Review Phase          (Optional)

1.      Prior to submission of an application for Board action, an applicant may request to meet with the Board or its designee for non-binding discussions beyond the conceptual and general stage, involving more specific design and engineering details of the potential application.

2.      The design review phase may proceed only after identification of and notice to abutters and the general public as required by RSA 676:4,I(d).

3.      Persons wishing to engage in preapplication design review shall submit a request to the Board not less than 15 days before the regularly scheduled meeting of the Board using the ‘Request for A Preapplication Review’ attached.  The request shall include:

a)      List of abutters and their addresses taken from municipal records not more than five (5) days before submission.

b)      Check to cover mailing and advertising costs.

4.      Statements made by Board members shall not be the basis for disqualifying said members or invalidating any action eventually taken on the application.

 

C.  Submission of Completed Application                     (Required)

1.      A completed application shall be filed with the Planning Board secretary at least 15 days before a regular meeting of the Board.  A completed application shall consist of all data required in Section V of these regulations.

2.      The Planning Board will review all plans for completeness.  This review may take place at a regular meeting of the Board, or by a person or persons designated to review plans for completeness prior to submission to the Board.  If the plan is incomplete, the applicant will need to provide the missing submission items before the Board will vote to accept the application.

3.      Submission and acceptance of an application shall only occur at a regular meeting of the Planning Board after due notification has been given according to RSA 686:4,I(d).  Acceptance will be by affirmative vote of a majority of the Board members present.

4.      When the Board has accepted a Completed Application, the Board shall provide a receipt to the Applicant indicating the date of acceptance, which is the start of the 90-day review.

 

D.     Board Action on completed Application

1.      The Board shall begin consideration of the Completed Application within 30 days of its acceptance.  The Board shall act to approve, conditionally approve, or disapprove the Accepted Application within 90 days of acceptance of the application.

2.      The Board may apply to the Selectmen for an extension not to exceed an additional 90 days before acting to approve, conditionally approve or disapprove an application.  An applicant may waive the requirement for Board action within the time periods specified in these regulations and consent to such extension as may be mutually agreeable.

November 14, 2000                                                                                                     SD

3.      Approval of the application shall be certified by written endorsement on the plat and signed and dated by the Chairman and Secretary of the Planning Board.  If any application is disapproved, the grounds for such disapproval shall be adequately stated in the records of the Planning Board and in written notice given to the Applicant within 72 hours of the decision.

4.      An approved plan shall be recorded by the Planning Board with the Register of Deeds of Cheshire County within 90 days of approval.  Any subdivision plan not filed within this time frame shall be considered void.

 

E.      Failure of the Planning Board to Act

1)      In the event that the Planning Board does not act on an accepted application within the prescribed 90 days, the applicant may petition the Selectmen to issue an order directing the Planning Board to act within 30 days.

2)      If the Planning Board fails to act within 40 days of this directive, the Selectmen must approve the application unless they find in writing that the plan does not comply with a local regulation.  In the event the Selectmen fail to act, the applicant may petition superior court to approve the plan.

 

F.      Conditional Approval

The Board may grant conditional approval of an application, but the plat will not be signed or recorded until all the conditions have been met.  If the applicant has not complied with the conditions of approval within one (1) year, the approval is considered null and void and the applicant must submit a new subdivision application.  A further public hearing is not required when such conditions:

1)      are administrative in nature

2)      involve no discretionary judgment on the part of the Board

3)      involve the applicant’s possession of permits and approvals granted by other boards or agencies, such as the Department of Transportation, the Wetlands Board, or Water Supply and Pollution Control Division; however, any subsequent change to the plan required such approvals would constitute grounds for a new application process.

 

G.     Expedited Review

1)      The Planning Board may allow for an expedited review of applications for lot line adjustments, technical subdivisions or minor subdivisions, as defined in Section II of these regulations.

2)      The Completed Application may be submitted, accepted and voted on at the same meeting provided the public notice so indicates.

3)      The Board may waive certain plat requirements for lot line adjustments, minor or technical subdivisions.

 

H.     Public Hearing

Prior to approval of a subdivision, a public hearing shall be held pursuant to RSA 676:4,I(d) with notice given to the applicant, abutters, and the public.  Public hearings may be waived for lot line adjustments.  Minor or technical subdivisions do not require public hearing unless requested by the Planning Board, the applicant or any abutters, except that public notice shall be given prior to approval of the application.  If a public hearing is to be held, it shall follow the procedures as outlined in Paragraph I of this section.

 

November 14, 2000                                                                                                     SD

I.        Notification

1)      Notice of a Design Review, submission of a Completed Application, or a Public Hearing shall be given by the Board to the abutters and the Applicant by certified mail, mailed at least ten (10) days prior to the submission.  The public will be given notice at the same time by posting at the Town Hall and the Post Office and publication in the Keene Sentinel.

2)      The notice shall give the date, time, and place of the Planning Board meeting at which the Application or other item(s) will be formally submitted to the Board, shall include a general description of the proposal which is to be considered, and shall identify the Applicant and the location of the proposal.

3)      If the notice for the public hearing was included in the notice of submission or any prior notice, additional notice of the public hearing is not required.  Additional notice is not required of an adjourned session of a hearing provided that the date, time, and place of the adjourned session was made known at the prior meeting.

 

J.       Fees

1)      A fee of $55.00 to reimburse the Board for its administrative and notification costs involved in processing applications shall accompany all applications.

2)      All costs of notices, whether mailed, posted, or published, shall be paid in advance by the Applicant.  Failure to pay costs shall constitute valid grounds for the Board to not accept the application as complete.

3)      All applicants are responsible for the recording cost at the Register of Deeds of Cheshire County of an approved, signed and dated plat.

4)      Pursuant to RSA 676:4,I(g), it shall be the responsibility of the Applicant, if the Board deems it necessary, to pay reasonable fees for special investigative studies, environmental assessments, legal review of documents, administrative expenses and other matters which may be required to make in informed decision on a particular application.  Failure to pay such costs shall constitute valid grounds for the Board to terminate further consideration of the application and to disapprove the plat without a public hearing.

 

K.    Site Inspections

1)      Whenever the Board deems it necessary for the consideration of an application to visit the site, the Board shall request permission from the applicant.  Inclusion of the public at the site inspection is at the discretion of the applicant.

2)      Such a site inspection shall be posted as a meeting of the Board pursuant to the Right-to-Know provisions of RSA 91-A.  If there is a quorum present at the site inspection, minutes shall be kept.

3)      All applications are conditioned upon the owner allowing access to the property, to the extent reasonable and necessary to properly review the application.  Denial of access automatically terminates any further consideration of the proposal.

 

L.      Concurrent and Joint Hearings.

The applicant may request a joint hearing with one or more land use boards in conjunction with a subdivision hearing if all are required for the same project.

 

 

 

 

 

January 3, 2002                                                                                                            SD

SECTION V               Submission Requirements

A.     A completed application shall consist of the following items unless a written waiver from the applicant has been granted by the Board: a completed application form, accompanied by (1) names and addresses of all abutters taken from the town records not more than five (5) days before the day of filing, and two (2) payment to cover filing and notification fees.  Four copies of the plat are required, prepared at any scale between 1” = 20’ and 1” = 400’.  The outside dimensions of the mylar shall be 17 x 22 inches, or 22 x 34 inches, except as may be otherwise specified by the Cheshire County Registry of Deeds.

B.      The plat shall show the following information depending on whether the proposed subdivision is Major or Minor: See Major or Minor Subdivision Checklist (attached) for requirements of proposed plat.

1.      Proposed subdivision name or identifying title: name and address of the applicant and of the owner, if other than the applicant.

2.      North arrow, scale, date of the plan, name and address and seal of the surveyor, signature block for Planning Board endorsement.

3.      Locus plan showing general location of the total tract within the town and the zoning district(s).

4.      Boundary survey including bearings, distances and the location of permanent markers.  The survey shall be conducted according to the standards outlined by the New Hampshire Land Surveyors Association.

5.      Location of property lines, including entire undivided lot, lot areas in square feet and acres, frontage on public rights-of-way, and building setback lines.  Each lot shall be numbered according to the Town tax map numbering system.

6.      Names of all abutting property owners, streets & other facts regarding abutting properties.

7.      Existing and proposed easements, rights-of-way, culverts, driveways and buildings or other structures.

8.      Water courses, ponds, standing water, rock ledges, stone walls and other natural features; existing and proposed foliage lines; and open space to be preserved. Wetlands resources, as defined by the town’s Wetland Resource Map (July 2002). These shall include public wells, intermittent and perennial water courses, wetland indicators including USGS Wetland Areas and USDA Hydric Soils, as well as the town’s wetland buffer zone.

9.      Existing and proposed streets with names, classification, travel surface widths and right-of-way widths.

10.  Final road profiles, center line stationing and cross sections.

11.  Existing and proposed topographic contours based upon the USGS topographical data with spot elevations where necessary.

1.      Soil data based on Cheshire County Soil Survey, including wetland delineation; and flood hazard areas.

2.      Location of percolation tests and test results; location of 75-foot well radius and 4,000 square-foot septic area.

3.      Base flood elevations.

 

A.     Other Information

1)      Plan for the control of sedimentation and erosion, if applicable.

2)      State septic design approval, copy of application, or certification by septic designer.

3)      State highway/Town driveway permits, as applicable.

4)      Any other state and/or federal permits.

5)      Any deed restrictions; and all deeds covering land to be used for public purposes, easements and rights-of-way over property to remain in private ownership, and

 

November 14, 2000                                                                                                     SD

rights of drainage across private property are submitted in a form satisfactory to the Board’s counsel.

6)      Any additional reports or studies deemed necessary by the Board to make an informed decision, including but not limited to: traffic, school, fiscal and environmental impact analyses.  The Board reserves the right to request such information after an application has been accepted as complete, as well as before acceptance.

 

 

SECTION VI             Developments Having Regional Impact

                                                (See list attached of criteria)

 

A.     All applications shall be reviewed for potential regional impacts.  Upon such a finding, the Board shall furnish the regional planning commission(s) and the affected municipalities with copies of the minutes of the meeting at which the determination was made.  The copies shall be sent by certified mail within 72 hours of the meeting.

B.     At least 14 days prior to the scheduled public hearing, the Board shall notify by certified mail the regional planning commission(s) and affected municipalities of the date, time and place of the hearing, and of their right to appear as abutters to offer testimony concerning the proposal.

 

 

SECTION VII                        Special Flood Hazard Areas    

 

A.     The Planning Board shall review the proposed development to assure that all necessary permits have been received from those governmental agencies from which approval is required by Federal or State law, including Section 404 of the Federal Water Pollution Control Act Amendments of 1972, 33 U.S.C. 1334.

B.     The Board shall require that all subdivision proposals and other proposed new developments greater than 50 lots or 5 acres, whichever is lesser, include within such proposals base flood elevation data.  Sufficient evidence (construction drawings, grading and land treatment plans) shall be submitted so as to allow determination that:

1)      all such proposals are consistent with the need to minimize flood damage; and

2)      adequate drainage is provided so as to reduce exposure to flood hazards.

 

 

SECTION VIII                      Performance Guarantee

 

A.         As a condition of approval, the Planning Board shall require the posting of a performance guarantee in an amount sufficient to defray the costs of construction of streets.  The amount of the security shall be based on an estimate of costs provided by the subdivider and, at the discretion of the Planning Board, reviewed by a licensed engineer.  The applicant shall pay all costs of such review.

B.         The Board and the municipal counsel shall approve the security as to form and sureties.  The amount of the security shall include feed to cover the cost of periodic inspections.

C.         Where electric lines or other utilities are to be installed by a corporation, municipal department, or public utility, a letter of intent shall be required stating that the work will be done in reasonable time and without expense to the Town.

 

November 14, 2000                                                                                                     SD

D.         Each approved plat shall contain a time limit for the completion of streets and public improvements.  The performance guarantee shall be released in phases as portions of the secured improvements or installations are completed and approved by the Board of its designee, in accordance with the plan approved by the Board.

 

SECTION IX             Revocation of Planning Board Approval

 

An approved and recorded subdivision plat may be revoked by the Board in whole or in part, under the following circumstances:  (1) at the request of or by agreement with the applicant; (2) when any requirement or condition of approval has been violated; (3) when the applicant has failed to perform any condition of approval within the time specified or within four years; (4) when four years have elapsed without any vesting of rights and the plan no longer conforms to applicable regulations; or (5) when the applicant has failed to provide for the continuation of adequate security.

 

SECTION X               Administration and Enforcement

 

A.     The Planning Board shall administer these regulations.  The enforcement of these regulations is vested with the Selectmen.

B.      Waivers:  The requirements of these regulations may be waived or modified when, in the opinion of the Board, specific circumstances surrounding subdivision, or the condition of the land in such subdivision, indicate that such modifications will properly carry out the purpose and intent of the master plan and these regulations.

C.     Penalties and Fines: Any violation of these regulations shall be subject to a civil fine as provided in RSA 676:16 and 676:17, as amended.

D.     Appeals:  Any person aggrieved by a decision of the Planning Board concerning a plat or subdivision may appeal said decision to the superior court pursuant to RSA 677:15, except when a disapproval by the Board is based upon non-compliance with the zoning ordinance.

 

SECTION XI             Validity

 

If any section or part of a section or paragraph of these regulations shall be declared invalid or unconstitutional, it shall not be held to invalidate or impair the validity, force or effect of any other section or part of a section or paragraph of these regulations.

 

SECTION XII                        Amendments

 

These regulations may be amended by a majority vote of the Planning Board after at least one (1) public hearing following the notification procedure outlined in Section IV, H & I.

 

SECTION XIII          Effective Date

 

These regulations and any amendments thereto shall take effect upon their adoption, and all regulations or parts of regulations, inconsistent therewith, are hereby repealed.

 

 

 

 

November 14, 2000                                                                                                     SD


CRITERIA FOR DETERMINING REGIONAL IMPACT

 

 

Impact Criteria shall include, but not be limited to, the following items: These shall in no way be considered exhaustive, but rather guidelines for the Board to follow in making a determination of impact on a neighboring municipality.

 

1.      Residential Development: Proposals for lots or dwellings that would increase the existing housing stock of the town by more than 25%.

 

2.      Commercial Development: Proposals for new or expanded space of 50,000 square feet or greater.

 

3.      Industrial Development: Proposals for new or expanded space of 100,000 square feet or more.

 

4.      Other Factors to be Considered:

A.     Proximity to other municipal boundaries.

B.     Traffic impacts on the regional road network.

C.     Potential effect on groundwater, surface water and wetlands that transcend municipal boundaries.

D.     The potential to disturb or destroy a significant or important natural environment or habitat.

E.      The necessity for shared public facilities such as schools or solid waste disposal.

F.      Anticipated emissions such as light, noise, smoke, odors, or particulates.

G.     The potential for accidents that would require evacuation of a large area.

H.     The generation and/or use of any hazardous materials.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

November 14, 2000                                                                                                     SD


TOWN OF WESTMORELAND

PLANNING BOARD

 

MINOR SUBDIVISION CHECKLIST

 

Applicant Name: ____________________________________  Date: _________________

 

The items on this page are considered to be the minimum requirements for a completed minor subdivision plat.  The Board may, in certain cases, need to request additional information.   

 

Submitted                                                                                                                     Waived

Yes     No                                                                                                                    Yes    No

 

____  ____      1.  Name of subdivision:  name and address of subdivider.                     ____  ____

 

____  ____      2.  Name, license number and seal of surveyor:  north arrow,     ____  ____

                                 scale, and date of plan.

 

____  ____      3.  Locus plan, showing zoning designations.                              ____  ____

 

____  ____      4.  Boundary survey and location of permanent markers.                       ____  ____

 

____  ____      5.  Location of property lines, lot areas in square feet and acres:            ____  ____

                                 setback lines: lots numbered according to tax map system.

 

____  ____      6.  Names of abutting property owners, streets, easements,                   ____  ____

                                 building lines, & other facts regarding abutting properties.

 

____  ____      7.  Existing and proposed easements, rights-of-way, driveways, ____  ____

                                 buildings, and other structures.

 

____  ____      8.  Water courses, ponds, standing water, rock ledges, stone walls        ____  ____

                                  & other natural features: existing and proposed foliage lines

                              and open space to be preserved. Wetland resources, as defined

                              by the town’s Wetland Resource Map (July 2002). These shall

                              include public wells, intermittent and perennial water courses,

                              wetland indicators including USGS Wetlands Areas and USDA

                              Hydric Soils, as well as the town’s wetland buffer zone.

 

____  ____      9.  Location of perc tests and test results and of 4,000 square-foot        ____  ____

                                 septic area: location of 75-foot well radius on property.

 

____  ____      10. Plan for control of sedimentation and erosion.                                  ____  ____

 

____  ____      11. Copy of state septic approval or certification from designer. ____  ____

                                 

____  ____      12. Copy of driveway permit.                                                               ____  ____

 

____  ____      13. Copy of any other state or federal permits.                          ____  ____

 

____  ____      14. Copy of deed restrictions.                                                               ____  ____

 

____  ____      15. Copy of deeds covering land to be used for public easements          ____  ____

                              and rights-of-way. 

TOWN OF WESTMORELAND

PLANNING BOARD

 

MAJOR SUBDIVISION CHECKLIST

 

Is this a Development having Regional Impact?  ____ Yes         ____  No

 

 

Applicant Name: ____________________________________  Date: _________________

 

The items on this page are considered to be the minimum requirements for a completed major subdivision plat.  The Board may, in certain cases, need to request additional information.   

 

Submitted                                                                                                                     Waived

Yes     No                                                                                                                    Yes    No

 

____  ____      1.  Name of subdivision:  name and address of subdivider.                     ____  ____

 

____  ____      2.  Name, license number and seal of surveyor:  north arrow,     ____  ____

                             scale, and date of plan.

 

____  ____      3.  Locus plan, showing zoning designations.                              ____  ____

 

____  ____      4.  Boundary survey and location of permanent markers.                       ____  ____

 

____  ____      5.  Location of property lines, lot areas in square feet and acres:            ____  ____

                             setback lines: lots numbered according to tax map system.

 

____  ____      6.  Names of abutting property owners, streets, easements,                   ____  ____

                             building lines, & other facts regarding abutting properties.

 

____  ____      7.  Existing and proposed easements, rights-of-way, driveways, ____  ____

                             buildings, and other structures.

 

____  ____      8.  Water courses, ponds, standing water, rock ledges, stone walls        ____  ____

                              & other natural features: existing and proposed foliage lines

                              and open space to be preserved. Wetland resources, as defined

                              by the town’s Wetland Resource Map (July 2002). These shall

                              include public wells, intermittent and perennial water courses,

                              wetland indicators including USGS Wetland Areas and UDSA

                              Hydric Soils, as well as the town’s wetland buffer zone.

                              

 

____  ____      9.  Existing and proposed street names, classifications, widths of            ____  ____

                             travel surface and right-of-way.

 

____  ____      10. Final road profiles, center line stationing and cross sections. ____  ____

 

____  ____      11. USGS contour lines at two-foot intervals.                            ____  ____

 

____  ____      12. Soil data, designating wetlands.                                                       ____  ____

(over)

 

Submitted                                                                                                                     Waived

Yes     No                                                                                                                    Yes    No

 

____  ____      13. Location of perc tests and test results and of 4,000 square-foot       ____  ____

                              septic area: location of 75-foot well radius on property.

 

 

____  ____      14. Plan for control of sedimentation and erosion.                                  ____  ____

 

____  ____      15. Copy of state septic approval or certification from designer. ____  ____

                         

____  ____      16. Copy of driveway permit.                                                               ____  ____

 

____  ____      17. Copy of any other state or federal permits.                          ____  ____

 

____  ____      18. Copy of deed restrictions.                                                               ____  ____

 

____  ____      19. Copy of deeds covering land to be used for public easements          ____  ____

                              and rights-of-way. 

 

____  ____      20. Any additional reports or studies.                                                    ____  ____

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TOWN OF WESTMORELAND

 

 

PLANNING BOARD

PO BOX 55

Westmoreland, NH  03467-0055

 

 

APPLICATION FOR LOT LINE/BOUNDARY ADJUSTMENT

 

                                                                                                Submission Date________________

 

Name of Property Owner applying for Adjustment: ____________________________________

 

Address: _______________________________________________Telephone: _____________

 

I, __________________________________ hereby apply for lot line/boundary adjustment and acknowledge I will comply with all the ordinances and any stipulations of the Planning Board of the Town of Westmoreland.

 

Location of property:                Map # ________         Lot # ________

 

Abutting property affected by lot line/boundary adjustment:

            (use back of application if more than one property is affected)

 

            Property Owner: __________________________________________________

 

            Address: _________________________________________________________

 

            Map # ________         Lot # ________

---------------------------------------------------------------------------------------------------------

Description of Proposed Request: (be complete as possible)

 

 

 

 

 

 

 

 

____________________________________

Signature of Applicant

 

---------------------------------------------------------------------------------------------------------

Note:  This application, together with three stamped copies of the plan of the property and a $55.00 Hearing fee, must be filed at least 15 days prior to the meeting with the Planning Board before consideration of lot line/boundary adjustment.  Recording costs will be paid by the applicant.

 

 

 

TOWN OF WESTMORELAND

 

 

PLANNING BOARD

PO BOX 55

Westmoreland, NH  03467-0055

 

 

REQUEST FOR A PREAPPLICATION REVIEW

 

OPTIONAL

 

(Used only for submission and informational purposes – not a public hearing)

 

 

                                                                                                Submission Date________________

 

 

Name of Property Owner applying for Adjustment: ____________________________________

 

 Address: _______________________________________________Telephone: _____________

 

Location of property:      Address ________________________________  Map # ____Lot # ____

 

 

      Notice is hereby given in accordance with RSA 676:4 that an application for            subdivision                    site plan            (please circle one) will be submitted to the Planning Board on __________

at the Westmoreland Town Hall during a regular meeting of the Board.  Upon a finding by the Board that the application meets the submission requirements of the Westmoreland subdivision and site plan regulations, the Board will vote to accept the application as complete and schedule a public hearing.  Should the application not be accepted as complete, another submission meeting will be scheduled.

 

 

 

 

 

________________________________________

Signature of Applicant

 

 

 

 

 

 

 

 

 

 

 

TOWN OF WESTMORELAND

 

 

PLANNING BOARD

PO BOX 55

Westmoreland, NH  03467-0055

 

 

APPLICATION FOR SUBDIVISION/SITE PLAN REVIEW

 

                                                                            

Submission Date________________

 

 

Name of Property Owner applying for Adjustment: _______________________________

 

 Address: __________________________________________Telephone: _____________

 

Location of property:      Address ___________________________  Map # ____Lot # ____

 

 

   I, __________________________________ hereby apply for a     subdivision        siteplan (please circle one) and acknowledge I will comply with all the ordinances of the Town of Westmoreland and any stipulations of the Planning Board as set forth in the appropriate ‘Subdivision/Site Plan Checklist’.

 

   Upon a finding by the Board that the application meets the submission requirements of the subdivision/site plan, the Board will vote to accept the application as complete, and a public hearing on the merits of the proposal will follow immediately.  Should the application be deemed incomplete or should a decision not be reached at the public hearing, this application will stay on the Planning Board agenda until such time as it is granted or not granted.

 

 

 

________________________________________

Signature of Applicant

 

 

 

 

 

 

 

 

 ---------------------------------------------------------------------------------------------------------

Note:  This application, together with three stamped copies of the plan of the property and a $55.00 hearing fee, must be filed at least 15 days prior to the meeting with the Planning Board before consideration of subdivision or site plan review.  Recording costs and postage, if applicable, will be paid by the applicant.